| Burlington
Transportation Planning as of
Fall 2005 |
SAFETEA Transportation Framework
Source:
Mike Monte, Director, CEDO
Downtown-Waterfront-Marketplace
Transportation Improvement Project
(DWM-TIP)
Draft
- September 2005
INTRODUCTION
The recent passage of the Federal Transportation bill provided two
earmarks for the Marketplace, Downtown and the Waterfront. In
addition to this appropriation, there are several other
transportation projects underway. The proposed framework provides
a rational approach to the planning and utilization of these
funds.
FRAMEWORK
In order to engage in a comprehensive program, the following is proposed:
Technical
Advisory Committee. Comprised of several departments of the City, this
existing group will conduct all planning and implementation
activities. Departments include: DPW, Parks, Planning, CEDO and
Arts. For the purposes of this exercise, the Committee will be
expanded to include the Marketplace, and to BED, as necessary.
Stakeholders
Group. This will be a new group and will include City Department Heads of the
departments above and other stakeholders including a
representative of the BBA, ECHO, Local Motion, CCTA, the Church
Street Marketplace Commission and others to be identified. This
group is advisory. It is assumed that the Commissions will be
actively engaged and will provide guidance to their respective
Department Heads.
Policy
and Final Approval. The Mayor and the City Council, through their budget
authority, and acting through the Finance Board and the
Council’s Transportation Committee, will have the final word on
the overall plan for implementation.
Management. CEDO is responsible for overall planning and coordination and for
central administrative functions. CEDO, in collaboration with DPW,
is responsible for compliance with all relative State and Federal
regulatory requirements. DPW and Parks will be responsible for
general construction management of all activities. The Church
Street Marketplace will be responsible for the management and
completion of the final phases of the Marketplace improvements
(Phase 3). Individual Departments will be tasked with leading
and implementing specific activities, as determined by the TAC.
Departments receiving “services” from other departments will
engage in Scope of Work Service Agreements that spell out the
specific responsibilities of each. Department Heads will be
responsible for reporting to their respective Commissions.
PRINCIPLES
The improvements that will be made will be guided by the following
principles:
1.
Burlington’s
Marketplace, Downtown and Waterfront will be economically
strengthened through continued public improvements and private
investments;
2.
The
infrastructure improvements provided on the Waterfront will ensure
safer pedestrian and vehicular access;
3.
The
amenities of the Marketplace will be extended to other parts of
the downtown and the waterfront;
4.
Consideration
will be given to improvements that can be well maintained and
managed.
BUDGET
This preliminary budget has been developed in order to illustrate
the Sources and Uses for this activity.
|
TRANSPORTATION
BUDGET
|
|
|
Original
|
Source
|
Federal
|
Match
|
Total
|
|
Waterfront
|
|
|
|
|
|
|
Pedestrian
Enhancements (Escarpements)
|
1,500,000
|
SAFETEA
|
500,000
|
100,000
|
600,000
|
|
Pedestrian and bicycle improvements (Depot Street)
|
1,500,000
|
SAFETEA
|
500,000
|
100,000
|
600,000
|
|
Lower College Street (Lake Street to Circle)
|
350,000
|
SAFETEA
|
750,000
|
150,000
|
900,000
|
|
“Moran Square” Infrastructure
|
2,500,000
|
SAFETEA
|
1,250,000
|
250,000
|
1,500,000
|
|
Undergrounding of Utilities
|
400,000
|
SAFETEA
|
250,000
|
50,000
|
300,000
|
|
Bike Path Improvements
|
|
SAFETEA
|
250,000
|
50,000
|
300,000
|
|
Total
Waterfront
|
|
|
3,500,000
|
700,000
|
4,200,000
|
|
|
|
|
|
|
|
|
Marketplace
|
|
|
|
|
|
|
PHASE
III A
|
|
|
|
|
|
|
Electrical
|
|
|
|
|
|
|
Electrical repair of boxes, cables
|
15,000
|
SAFETEA
|
15,000
|
3,000
|
18,000
|
|
Light pole and base replacement
|
130,000
|
SAFETEA
|
130,000
|
26,000
|
156,000
|
|
Electrical conduit and vault replacement
|
500,000
|
SAFETEA
|
500,000
|
100,000
|
600,000
|
|
Intersection
& Side Street Enhancements
|
|
|
|
|
|
|
Cables and banners
|
50,000
|
SAFETEA
|
50,000
|
10,000
|
60,000
|
|
Information
Directory
|
|
|
|
|
|
|
Info Kiosk, including ATM
|
125,000
|
SAFETEA
|
125,000
|
25,000
|
150,000
|
|
Intersection
& Side Street Enhancements
|
|
|
|
|
|
|
Cherry Street intersection bricking
|
80,000
|
SAFETEA
|
80,000
|
16,000
|
96,000
|
|
Arts
Alley
|
|
|
|
|
|
|
Arts alley paving
|
50,000
|
SAFETEA
|
50,000
|
10,000
|
60,000
|
|
Arts alley improvements
|
100,000
|
SAFETEA
|
100,000
|
20,000
|
120,000
|
|
Public Art
|
50,000
|
SAFETEA
|
50,000
|
10,000
|
60,000
|
|
Addition to storage/shop area
|
25,000
|
SAFETEA
|
25,000
|
5,000
|
30,000
|
|
City Hall fountain
|
150,000
|
SAFETEA
|
150,000
|
30,000
|
180,000
|
|
PHASE
III B
|
|
|
|
|
|
|
Fountains
|
|
|
|
|
|
|
Top Block fountain
|
150,000
|
SAFETEA
|
150,000
|
30,000
|
180,000
|
|
Information
Directory
|
|
|
|
|
|
|
Info Kiosk, including ATM
|
125,000
|
SAFETEA
|
125,000
|
25,000
|
150,000
|
|
Brick
Replacement
|
|
|
|
|
|
|
Replace damaged brick Mall Block
|
242,000
|
SAFETEA
|
242,000
|
48,400
|
290,400
|
|
Replace damaged brick Second Block
|
295,000
|
SAFETEA
|
295,000
|
59,000
|
354,000
|
|
Replace damaged brick Top Block
|
75,000
|
SAFETEA
|
75,000
|
15,000
|
90,000
|
|
Intersection
& Side Street Enhancements
|
|
|
|
|
|
|
Pearl Street gateway
|
100,000
|
SAFETEA
|
90,000
|
18,000
|
108,000
|
|
Main Street gateway
|
100,000
|
SAFETEA
|
90,000
|
18,000
|
108,000
|
|
Cherry, Bank & College Street gateways
|
200,000
|
SAFETEA
|
185,000
|
37,000
|
222,000
|
|
Amenities
replacement
|
|
|
|
|
|
|
Replacement benches
|
20,000
|
SAFETEA
|
20,000
|
4,000
|
24,000
|
|
Replacement trees
|
60,000
|
SAFETEA
|
42,000
|
8,400
|
50,400
|
|
PHASE
III C
|
|
|
|
|
|
|
Market-Based Study
|
|
|
50,000
|
10,000
|
60,000
|
|
Total
Marketplace
|
|
|
2,589,000
|
517,800
|
3,106,800
|
|
|
|
|
|
|
|
|
Downtown
|
|
|
|
|
|
|
College Street enhancement
|
1,000,000
|
SAFETEA
|
1,000,000
|
200,000
|
1,200,000
|
|
Cherry Street enhancement
|
1,000,000
|
SAFETEA
|
1,000,000
|
200,000
|
1,200,000
|
|
Bank Street enhancement
|
1,000,000
|
SAFETEA
|
1,000,000
|
200,000
|
1,200,000
|
|
Total
Downtown
|
|
|
3,000,000
|
600,000
|
3,600,000
|
|
|
|
|
|
|
|
|
Planning,
Administration, Management
|
|
SAFETEA
|
411,000
|
82,200
|
493,200
|
|
Transit
Center
|
2,500,000
|
FTA
|
3,240,000
|
760,000
|
4,000,000
|
|
Battery
Park Extension
|
260,000
|
ICETEA
|
180,000
|
70,000
|
250,000
|
|
TOTAL
|
12,920,000
|
2,730,000
|
15,650,000
|
Return to Top
City
of Burlington
Summary
of Major Transportation Initiatives as of November 2005
Source:
Mike Monte, Director, CEDO
A.
Major Roads: North Street completed, Riverside Avenue
underway and the Southern Connector scheduled to start construction
next year. The Route 2 corridor from South Willard Street to
Williston Village will undergo extensive analysis and planning.
Implementation of major projects will be supported by funds
earmarked for improvements to the interchange at I89.
B.
Downtown Public Transit Improvements: Funds have been secured
for the redevelopment of the Downtown Transit Center.
C.
Auto Capture and Park and Ride facilities: Planning has begun
for expansion of the South End Transit Center, an auto capture multi
modal facility in the South End. Similar facilities are planned
adjacent to Exits 14 and 16.
D.
Pedestrian Improvements: $9.5 million has been secured ($6M
for Church Street and Downtown Improvements and $3.5M for the
Waterfront). Planning for improvements to Battery Street Extension
is underway.
E.
Parking: Renovations completed at Church Street Marketplace
Garage. The Wyndham Garage is next. The Lakeview Garage has been
expanded. The City’s Parking Study calls for additional public
parking at the corner of Winooski and Main Street. Scoping has
begun.
F.
Rail: The state has secured funds for improvements to be
prioritized by the legislature. Relocation of the Burlington rail
yard is one of the eligible projects.
G.
Transportation Plan: We have secured funds to develop a
comprehensive transportation capital plan. We will solicit
consultant proposals shortly.
H.
CCTA Improvements: CCTA has streamlined service in the Pine
Street corridor and is developing plans for increased service
between Downtown Winooski and the Waterfront.
I.
Pedestrian Summit: Comments
solicited at special events and on line at the City’s web site
will comprise a list of recommendations and suggestions for
improvement to the City’s pedestrian system.
J.
Alternative Fuels: Construction begins on a hydrogen fueling
station at DPW on 11/9. Bids on a compressed natural gas (CNG)
facility are due 11/28. Bio diesel remains under consideration.
K.
Bicycle improvements: A south bound bike lane has been added
along South Winooski Avenue. A north bound lane may be established
next spring. With the
completion of the Downtown Winooski project interest in establishing
connections across the river have been rekindled.
L.
Intervale Road: Scoping is near complete on improvements from
Riverside Avenue to the Intervale.
M.
North Winooski Avenue: Enhancement grant funded Streetscape
improvements from Riverside Avenue to Archibald Street to begin next
spring.
N.
Route 127 North Avenue: Scoping completed with City Council
and DPW Commission preferred alternative of a modified slip ramp
seeking funding through the MPO and local sources.
Return
to Top
###
Downtown
Waterfront in Burlington's Ten Year Transportation Action Plan
Source:
Dan Bradley, Special Projects Director, Department of Public Works,
November 2005
PROJECT
UNDERSTANDING AND APPROACH
The
purpose of this project is to develop a multi-modal transportation
improvement plan that accounts for the changes anticipated within
the Burlington Downtown and Waterfront and addresses specific
deficiencies. The outcome will be a comprehensive and coordinated
list of roadway, transit, bicycle and pedestrian facility,
streetscape and land use recommendations for implementation that
satisfy an overall Downtown Waterfront vision.
The
Downtown Waterfront element of the Ten Year Transportation Action
Plan will be developed in the context of a growing metropolitan
region. As the region’s core city, the region depends on the City
of Burlington as its economic engine. At the same time, the City
depends on the region for its commuter base and broad retail
customer base. Strong transit and roadway connections between the
City and the region and sustainable pedestrian level linkages and
amenities within the Downtown Waterfront area which are appropriate
for the vision and goals of the city are critical to maintaining an
economically healthy city and an economically healthy region and
state.
The
scope of work should address the relationship between the Downtown
and Waterfront’s transportation system and land use, the need to
incorporate multiple stakeholders, and the desire to create a
practical plan with recommendations that can be implemented. The
scope will provide:
•
State-of-the-Art
transportation planning and engineering tools and techniques;
•
A
market-based approach to assessing, planning for, and recommending
land use policies;
•
Development
of specific goals;
•
A
multi-disciplinary approach that includes transportation planning,
traffic engineering, roadway design, land use planning, landscape
architecture, and project implementation;
•
A
public outreach plan that gathers input at multiple levels including
regular Steering
Committee
meetings, Downtown Waterfront wide public meetings, and meetings
with stakeholders
•
Development
of a realistic implementation plan; and
•
Development
of a realistic and sustainable operations and maintenance plan.
SCOPE
OF WORK
This
scope of work will be designed with the following four major phases:
•
Phase
I-Analysis of Existing and Future Issues and Development of Downtown
Waterfront Vision/Goals;
•
Phase
II-Evaluation of Strategies;
•
Phase
III-Development of Implementation Plan; and
•
Phase IV-Development of an Operations and Maintenance plan.
Each
phase has multiple deliverables and meetings to allow for project
tracking and continuous feedback from the Steering Committee. The
first two phases will produce Phase I and Phase II reports that can
be stand-alone documents. In the event that the City decides not to
continue with the plan beyond the first two phases, the Phase I and
Phase II reports would have sufficient “shelf life” such that
the City could resume the project after a few years without needing
to start from the beginning. The final plan will be produced at the
end of Phase IV.
STUDY
LEVEL OF DETAIL
Traffic
volume projections, capacity analyses, access management assessment,
and bicycle and pedestrian facility assessment will be conducted and
roadway, intersection, streetscape, pedestrian and bicycle facility
design concepts will be prepared for the study area.
Updated December 13, 2005
|