Burlington Transportation Planning as of       Fall 2005

City Framework for Planning for Use of Federal Funds

Preliminary Budget for Federal Transportation Funds

Summary of Major Transportation Initiatives

Downtown Waterfront Transportation Planning Project

Return to Issues & Information Links

BBA 4th Annual Business Summit - Jan 5, 2006

 

SAFETEA Transportation Framework

Source: Mike Monte, Director, CEDO

Downtown-Waterfront-Marketplace Transportation Improvement Project (DWM-TIP)

Draft - September 2005 

INTRODUCTION

The recent passage of the Federal Transportation bill provided two earmarks for the Marketplace, Downtown and the Waterfront. In addition to this appropriation, there are several other transportation projects underway. The proposed framework provides a rational approach to the planning and utilization of these funds. 

FRAMEWORK

In order to engage in a comprehensive program, the following is proposed: 

Technical Advisory Committee. Comprised of several departments of the City, this existing group will conduct all planning and implementation activities. Departments include: DPW, Parks, Planning, CEDO and Arts. For the purposes of this exercise, the Committee will be expanded to include the Marketplace, and to BED, as necessary.  

Stakeholders Group. This will be a new group and will include City Department Heads of the departments above and other stakeholders including a representative of the BBA, ECHO, Local Motion, CCTA, the Church Street Marketplace Commission and others to be identified. This group is advisory. It is assumed that the Commissions will be actively engaged and will provide guidance to their respective Department Heads. 

Policy and Final Approval. The Mayor and the City Council, through their budget authority, and acting through the Finance Board and the Council’s Transportation Committee, will have the final word on the overall plan for implementation. 

Management. CEDO is responsible for overall planning and coordination and for central administrative functions. CEDO, in collaboration with DPW, is responsible for compliance with all relative State and Federal regulatory requirements. DPW and Parks will be responsible for general construction management of all activities. The Church Street Marketplace will be responsible for the management and completion of the final phases of the Marketplace improvements (Phase 3). Individual Departments will be tasked with leading and implementing specific activities, as determined by the TAC. Departments receiving “services” from other departments will engage in Scope of Work Service Agreements that spell out the specific responsibilities of each. Department Heads will be responsible for reporting to their respective Commissions. 

PRINCIPLES

The improvements that will be made will be guided by the following principles:

1.      Burlington’s Marketplace, Downtown and Waterfront will be economically strengthened through continued public improvements and private investments;

2.      The infrastructure improvements provided on the Waterfront will ensure safer pedestrian and vehicular access;

3.      The amenities of the Marketplace will be extended to other parts of the downtown and the waterfront;

4.      Consideration will be given to improvements that can be well maintained and managed. 

BUDGET

This preliminary budget  has been developed in order to illustrate the Sources and Uses for this activity. 


TRANSPORTATION BUDGET

 

 Original 

 Source

 Federal

 Match

 Total

 Waterfront

 

 

 

 

 

 Pedestrian Enhancements (Escarpements)

 1,500,000

 SAFETEA

         500,000

         100,000

         600,000

 Pedestrian and bicycle improvements  (Depot Street)

 1,500,000

 SAFETEA

         500,000

         100,000

         600,000

 Lower College Street (Lake Street to Circle)

    350,000

 SAFETEA

         750,000

         150,000

         900,000

  “Moran Square” Infrastructure 

 2,500,000

 SAFETEA

      1,250,000

         250,000

      1,500,000

 Undergrounding of Utilities

    400,000

 SAFETEA

         250,000

          50,000

         300,000

 Bike Path Improvements

 

 SAFETEA

         250,000

          50,000

         300,000

 Total Waterfront

 

 

      3,500,000

         700,000

      4,200,000

 

 

 

 

 

 

  Marketplace

 

 

 

 

 

 PHASE III A

 

 

 

 

 

 Electrical

 

 

 

 

 

 Electrical repair of boxes, cables

      15,000

SAFETEA

      15,000

            3,000

          18,000

 Light pole and base replacement

    130,000

 SAFETEA

         130,000

          26,000

         156,000

 Electrical conduit and vault replacement

    500,000

 SAFETEA

         500,000

         100,000

         600,000

 Intersection & Side Street Enhancements 

 

 

 

 

 

 Cables and banners

      50,000

 SAFETEA

          50,000

          10,000

          60,000

 Information Directory

 

 

 

 

 

 Info Kiosk, including ATM

    125,000

 SAFETEA

         125,000

          25,000

         150,000

 Intersection & Side Street Enhancements 

 

 

 

 

 

 Cherry Street intersection bricking

      80,000

 SAFETEA

          80,000

          16,000

          96,000

 Arts Alley

 

 

 

 

 

 Arts alley paving

      50,000

 SAFETEA

          50,000

          10,000

          60,000

 Arts alley improvements

    100,000

 SAFETEA

         100,000

          20,000

         120,000

 Public Art

      50,000

 SAFETEA

          50,000

          10,000

          60,000

 Addition to storage/shop area

      25,000

 SAFETEA

          25,000

            5,000

          30,000

 City Hall fountain

    150,000

 SAFETEA

         150,000

          30,000

         180,000

 PHASE III B

 

 

 

 

 

 Fountains

 

 

 

 

 

 Top Block fountain

    150,000

 SAFETEA

         150,000

          30,000

         180,000

 Information Directory

 

 

 

 

 

 Info Kiosk, including ATM

    125,000

 SAFETEA

         125,000

          25,000

         150,000

 Brick Replacement

 

 

 

 

 

 Replace damaged brick Mall Block

    242,000

 SAFETEA

         242,000

          48,400

         290,400

 Replace damaged brick Second Block

    295,000

 SAFETEA

         295,000

          59,000

         354,000

 Replace damaged brick Top Block

      75,000

 SAFETEA

          75,000

          15,000

          90,000

 Intersection & Side Street Enhancements 

 

 

 

 

 

 Pearl Street gateway

    100,000

 SAFETEA

          90,000

          18,000

         108,000

 Main Street gateway

    100,000

 SAFETEA

          90,000

          18,000

         108,000

 Cherry, Bank & College Street gateways

    200,000

 SAFETEA

         185,000

          37,000

         222,000

 Amenities replacement

 

 

 

 

 

 Replacement benches

      20,000

 SAFETEA

          20,000

            4,000

          24,000

 Replacement trees

      60,000

 SAFETEA

          42,000

            8,400

          50,400

 PHASE III C

 

 

 

 

 

 Market-Based Study

 

 

          50,000

          10,000

          60,000

 Total Marketplace

 

 

      2,589,000

         517,800

      3,106,800

 

 

 

 

 

 

Downtown 

 

 

 

 

 

 College Street enhancement

 1,000,000

 SAFETEA

      1,000,000

         200,000

      1,200,000

 Cherry Street enhancement

 1,000,000

 SAFETEA

      1,000,000

         200,000

      1,200,000

 Bank Street enhancement

 1,000,000

 SAFETEA

      1,000,000

         200,000

      1,200,000

 Total Downtown

 

 

      3,000,000

         600,000

      3,600,000

 

 

 

 

 

 

Planning, Administration, Management 

 

 SAFETEA

         411,000

          82,200

         493,200

 Transit Center

 2,500,000

 FTA

      3,240,000

         760,000

      4,000,000

 Battery Park Extension

    260,000

 ICETEA

         180,000

          70,000

         250,000

 TOTAL

    12,920,000

      2,730,000

    15,650,000


Return to Top

###

City of Burlington

Summary of Major Transportation Initiatives as of November 2005 

Source: Mike Monte, Director, CEDO

A.      Major Roads: North Street completed, Riverside Avenue underway and the Southern Connector scheduled to start construction next year. The Route 2 corridor from South Willard Street to Williston Village will undergo extensive analysis and planning. Implementation of major projects will be supported by funds earmarked for improvements to the interchange at I89.

 

B.     Downtown Public Transit Improvements: Funds have been secured for the redevelopment of the Downtown Transit Center.

 

C.     Auto Capture and Park and Ride facilities: Planning has begun for expansion of the South End Transit Center, an auto capture multi modal facility in the South End. Similar facilities are planned adjacent to Exits 14 and 16.

 

D.     Pedestrian Improvements: $9.5 million has been secured ($6M for Church Street and Downtown Improvements and $3.5M for the Waterfront). Planning for improvements to Battery Street Extension is underway.

 

E.     Parking: Renovations completed at Church Street Marketplace Garage. The Wyndham Garage is next. The Lakeview Garage has been expanded. The City’s Parking Study calls for additional public parking at the corner of Winooski and Main Street. Scoping has begun.

 

F.      Rail: The state has secured funds for improvements to be prioritized by the legislature. Relocation of the Burlington rail yard is one of the eligible projects.

 

G.     Transportation Plan: We have secured funds to develop a comprehensive transportation capital plan. We will solicit consultant proposals shortly.

 

H.     CCTA Improvements: CCTA has streamlined service in the Pine Street corridor and is developing plans for increased service between Downtown Winooski and the Waterfront.

 

I.         Pedestrian Summit: Comments solicited at special events and on line at the City’s web site will comprise a list of recommendations and suggestions for improvement to the City’s pedestrian system.

 

J.       Alternative Fuels: Construction begins on a hydrogen fueling station at DPW on 11/9. Bids on a compressed natural gas (CNG) facility are due 11/28. Bio diesel remains under consideration.

 

K.     Bicycle improvements: A south bound bike lane has been added along South Winooski Avenue. A north bound lane may be established next spring.  With the completion of the Downtown Winooski project interest in establishing connections across the river have been rekindled.

 

L.      Intervale Road: Scoping is near complete on improvements from Riverside Avenue to the Intervale.

 

M.     North Winooski Avenue: Enhancement grant funded Streetscape improvements from Riverside Avenue to Archibald Street to begin next spring.

 

N.     Route 127 North Avenue: Scoping completed with City Council and DPW Commission preferred alternative of a modified slip ramp seeking funding through the MPO and local sources.

 

Return to Top

###

Downtown Waterfront in Burlington's Ten Year Transportation Action Plan

Source: Dan Bradley, Special Projects Director, Department of Public Works, November 2005

PROJECT UNDERSTANDING AND APPROACH

The purpose of this project is to develop a multi-modal transportation improvement plan that accounts for the changes anticipated within the Burlington Downtown and Waterfront and addresses specific deficiencies. The outcome will be a comprehensive and coordinated list of roadway, transit, bicycle and pedestrian facility, streetscape and land use recommendations for implementation that satisfy an overall Downtown Waterfront vision. 

The Downtown Waterfront element of the Ten Year Transportation Action Plan will be developed in the context of a growing metropolitan region. As the region’s core city, the region depends on the City of Burlington as its economic engine. At the same time, the City depends on the region for its commuter base and broad retail customer base. Strong transit and roadway connections between the City and the region and sustainable pedestrian level linkages and amenities within the Downtown Waterfront area which are appropriate for the vision and goals of the city are critical to maintaining an economically healthy city and an economically healthy region and state. 

The scope of work should address the relationship between the Downtown and Waterfront’s transportation system and land use, the need to incorporate multiple stakeholders, and the desire to create a practical plan with recommendations that can be implemented. The scope will provide: 

State-of-the-Art transportation planning and engineering tools and techniques;

A market-based approach to assessing, planning for, and recommending land use policies;

Development of specific goals;

A multi-disciplinary approach that includes transportation planning, traffic engineering, roadway design, land use planning, landscape architecture, and project implementation;

A public outreach plan that gathers input at multiple levels including regular Steering

Committee meetings, Downtown Waterfront wide public meetings, and meetings with stakeholders

Development of a realistic implementation plan; and

Development of a realistic and sustainable operations and maintenance plan. 

SCOPE OF WORK

This scope of work will be designed with the following four major phases:

Phase I-Analysis of Existing and Future Issues and Development of Downtown Waterfront Vision/Goals;

Phase II-Evaluation of Strategies;

Phase III-Development of Implementation Plan; and

• Phase IV-Development of an Operations and Maintenance plan. 

Each phase has multiple deliverables and meetings to allow for project tracking and continuous feedback from the Steering Committee. The first two phases will produce Phase I and Phase II reports that can be stand-alone documents. In the event that the City decides not to continue with the plan beyond the first two phases, the Phase I and Phase II reports would have sufficient “shelf life” such that the City could resume the project after a few years without needing to start from the beginning. The final plan will be produced at the end of Phase IV. 

STUDY LEVEL OF DETAIL

Traffic volume projections, capacity analyses, access management assessment, and bicycle and pedestrian facility assessment will be conducted and roadway, intersection, streetscape, pedestrian and bicycle facility design concepts will be prepared for the study area.

 

Updated December 13, 2005